RM06-16-000, RD09-1-000
Status Report on VSLs for TOP-004-2

NERC submitted a status report on submitting the revised VSLs for TOP-004-2.  Docket Nos. RM06-16-000 and RD09-1-000​

12/31/2008
RR08-4-000, RR08-4-001, RR08-4-002
Compliance Filing in Response to Paragraph 47 of the June 19, 2008 Order
NERC submits a compliance filing that provides a justification for the inconsistencies in the single VSL assigned to binary requirements; or alternatively, NERC may either (1) modify the single VSL by consistently applying the same severity level or (2) modify the VSL assignment by changing from a binary approach to an approach using gradation.  Docket Nos. RR08-4-000, RR08-4-001 and RR08-4-002​
12/19/2008
RR08-4-000, RR08-4-001, RR08-4-002
Compliance Filing in Response to Paragraph 76 of the November 20, 2008 Order

NERC submits a compliance filing in response to the November 20 Order on Rehearing and Clarification and Accepting Compliance Filing.  NERC submits six modified VSLs in response to Paragraph 76 of the November 20 Order.  Docket Nos. RR08-4-000, RR08-4-001 and RR08-4-002​

12/19/2008
RM06-22-000
Supplemental Compliance Filing in Response to Paragraphs 751 and 757 - submission of 31 CIP VRFs

NERC submits this supplemental filing to include Violation Risk Factors for thirty-one Requirements or Sub-Requirements in the Critical Infrastructure Protection (“CIP”) Reliability Standards CIP-002-1 through CIP-009-1 that have been approved by the Commission.  Docket No. RM06-22-000​

12/19/2008
RR08-6, RR07-14
Compliance Filing in response to the October 16, 2008 Order on the 2009 Business Plan and Budget Filing

NERC submits a compliance filing in Response to the October 16 2008 Commission Order on 2009 Business Plans and Budgets. Docket Nos. RR08-6 and RR07-14​

12/15/2008
RC08-5-001
Errata to November 20, 2008 Filing

NERC submits an errata Filing to November 20, 2008 Motion for Leave to Answer and Answer of the North American Electric Reliability Corporation, Docket No. RC08-5-001​

12/1/2008
RM08-11-000
Comments on the NOPR for Version Two FAC Standards

NERC submitted comments in response to the Commission's October 16, 2008 Notice of Proposed Rulemaking to address the Version Two FAC Reliability Standards.  Docket No. RM08-11-000​

11/24/2008
RM05-17-000, RM05-25-000
Compliance Filing in Response to Paragraph 223 of Order No. 890

NERC submits a compliance filing in Response to Paragraph 223 of Order No. 90 and Request for Approval of Proposed Reliability Standard – MOD-004-1.  Docket Nos. RM05-17-000 & RM05-25-000​

11/21/2008
RR06-1-012, RR06-1-018, RR07-7-002, RR07-7-006, RR09-1-000
Further Status Report of NERC and WECC in response to P 226 of the March 21, 2008 Order

NERC and WECC file this further status report in response to P 226 of the Commission’s Order issued March 21, 2008.  NERC and WECC filed an initial status report on September 22, 2008. NERC and WECC are now filing this further status report to submit the agreement NERC and WECC have entered into pursuant to which NERC will perform all CMEP responsibilities with respect to the WECC RC function. Docket Nos. RR06-1-012, RR06-1-018, RR07-7-002, RR07-7-006 and RR09-1-000​

11/21/2008
RC08-5-001
Motion to Answer and NERC's Answer of DOE/PPPO's Comments

NERC submits its motion to answer and answers the comments submitted by the United States
Department of Energy Portsmouth/Paducah Project Office (“DOE/PPPO”) in response to NERC's October 5, 2008 Intervention.  Docket No. RC08-5-001​

11/20/2008
RM08-3-002
Compliance Filing in response to P 107 Order No. 716

NERC submits a filing in compliance with paragraph 107 of Order No. 716 that required NERC to submit a timeline for developing and filing a modification to Requirement R9.3.5 of Reliability Standard NUC-001-1. Docket No. RM08-3-002​

11/17/2008
RR08-6-001 et al.
Request for Clarification of Paragraphs 24-25 of October 16, 2008 Order on 2009 Business Plan and Budget

NERC submits a Request for Clarification of Paragraphs 24-25 of October 16, 2008 Order on 2009 Business Plan and Budget. Docket Nos. RR08-6-001 et al.​

11/14/2008
RM06-22-000
Comments in Response to the Commission's September 18, 2008 Order on Proposed Clarification

NERC submits comments in response to the September 18, 2008 Order. The Commission proposed to clarify the scope of the eight CIP Reliability Standards approved in Order No. 706 to ensure that no “gap” occurs in the applicability of these Standards to nuclear generating plants.  Docket No. RM06-22-000

11/3/2008
RC09-1-000
2008 Long-Term Reliability Assessment

NERC submits the 2008 Long-Term Reliability Assessment.  Docket No. RC09-1-000​

10/31/2008
RM06-16-006
Compliance Filing in Response to Paragraph 951 of Order No. 693

NERC submits the results of the Interconnection Reliability Operating Limit survey conducted from August 18, 2007 through August 17, 2008. The Commission directed NERC to conduct a year-long survey of the IROL practices and actual operating experiences beginning August 18, 2007 through August 17, 2008. Docket No. RM06-16-006​

10/31/2008
RR06-1-000
Quarterly Report Regarding Analysis of Reliability Standards Voting Results July - September 2008

NERC submits its Quarterly Report Regarding Analysis of Reliability Standards Voting Results July – September 2008.  Docket No. RR06-1-000​

10/31/2008
RM08-7-001
Motion for Leave to Answer and Answer

NERC submits answers in response to comments submitted by NRG Companies on October 10, 2008 regarding NERC's September 11, 2008 Compliance Filing in response to paragraph 50 of the Commission's July 21, 2008 Order No. 713, which directed NERC to provide an explanation regarding Requirements R1 and R1.1 of IRO-006-4.  Docket No. RM08-7-001​

10/27/2008
RD09-4-000
Petition of NERC for Approval of Formal Interpretations to Reliability Standards

NERC submits for approval interpretations to requirements of two Commission-approved Reliability Standards, Requirements R1.3.2 and R 1.3.12 of TPL-002-0 and TPL-003-0.  Docket No. RD09-4-000​

10/24/2008
RM08-11-000
Supplemental Filing - Violation Risk Factors for Version 2 FAC Standards

NERC requests that the Commission accept the VRFs filed for the FAC-010-1, FAC-011-1 and FAC-014-1 version 1 as the applicable VRFs for version 2 of the FAC Reliability Standards. A chart identifying the applicable VRFs is set forth in Exhibit A. A complete matrix of all of the VRFs is set forth in Exhibit B. Docket No. RM08-11-000​

10/15/2008
RC08-7-001
Motion to Leave to Answer and Answer Comments Filed by SENA

NERC submits leave to answer and answer the comments submitted by Shell Energy North America (US), L.P. (SENA) in the Constellation Energy Commodities Group, Inc. Docket No. RC08-7-001​

10/8/2008
RC08-5-001
Compliance Registry Appeal Decision on Remand

NERC submits a decision on remand in response to the Commission’s July 21, 2008 Order regarding the appeal involving the United States Department of Energy, Portsmouth/Paducah Project Office (DOE/PPPO). In the July 21 Order, the Commission upheld DOE/PPPO’s TO, TOP and DP; the Commission also remanded the proceedings to NERC for further consideration on the issue whether DOE/PPPO was properly registered as an LSE. Docket No. RC08-5-001​

10/6/2008
RR07-7-
Petition for Approval of Revisions to Exhibit E to WECC's Delegation Agreement

NERC requests Commission approval of two revisions to Exhibit E to the delegation agreement between NERC and WECC. Docket No. RR07-7-​

9/30/2008
Status Report of NERC and WECC in Response to Paragraph 226 of the March 21 Order

NERC and WECC filed a status report in response to paragraph 226 of the March 21 Order.  The Commission directed NERC and WECC to submit this report six months following the date of the Order, and every six months thereafter as necessary, concerning the steps being taken by NERC and WECC to reach a permanent solution for the need to maintain appropriate separation between WECC's compliance monitoring and enforcement activities and its reliability coordination function.​

9/22/2008
RC07-4-003, et al.
Motion for Leave to File an Answer and Answer

NERC submits an answer to comments received in response to NERC's July 31, 2008 Compliance Filing regarding the proposed revision to the NERC Statement of Compliance Registry Criteria.  Docket Nos. RC07-4-003, et al.​

9/17/2008
RR06-1-017, et al.
Supplemental Response to Comments in Response to NERC's July 21 Compliance Filing

NERC submits a supplemental filing in response to the comments TAPS submitted on August 11, 2008 in response to NERC's July 21, 2008 compliance filing regarding the revised Delegation Agreements, CMEP and Rules of Procedure.  Docket Nos. RR06-1-017, et al.​

9/15/2008
RM08-7-000
Compliance Filing in Response to Paragraph 50 of Order No. 713

Compliance filing in response to paragraph 50 of Order No. 713.  The Commission directed NERC to provide an explanation regarding Requirements R1 and R1.1 of IRO-006- 4 Reliability Standard.  Docket No.  RM08-7-000.​

9/11/2008
RR08-6-000
Motion to Submit Correction to the 2009 Business Plan and Budget Filing

NERC submits a corrected version of the 2009 Business Plan and Budget filing that was made on August 22, 2008.  Docket No. RR08-6-000​

9/2/2008
RM08-19-000
Compliance Filing in Response to Paragraph 223 of Order No. 890

NERC requests the Commission to approve five proposed Reliability Standards (MOD-001-1, MOD-008-1, MOD-028-1, MOD-029-1, MOD-030-1 and two modifications to Commission-approved definitions and 18 new definitions in response to paragraph 223 of the Commission's Order No. 890.  Docket No. RM08-19-000​

8/29/2008
RR06-1-017, RR07-4-004
Motion to file corrected Attachment 7 to Compliance Filing in response to March 21 Order

NERC files a corrected version 7 of Attachment 7 (Amended and Restated Delegation Agreement between NERC and RFC) to the Compliance Filing filed July 21, 2008 in response to the March 21 Order.  Docket Nos. RR06-1-017 and RR07-4-004 ​

8/28/2008
RR08-7-000
Petition for approval of proposed revisions to the RFC Bylaws

NERC requests approval of amendments to the Bylaws of ReliabilityFirst Corporation.  Docket No. RR08-7-000​

8/28/2008
RR06-1-017, RR07-7-004
Supplement to Compliance Filing in Response to March 21, 2008 Order

NERC submits a revised amended and restated delegation agreement between NERC and WECC in response to the March 21, 2008 Order.  Docket Nos. RR06-1-017 and RR07-7-004​

8/28/2008
RR08-6-000
Request of NERC for Acceptance of its and the Regional Entities 2009 Business Plans and Budgets

NERC submits the proposed business plans and budgets of NERC and the Regional Entities to the Commission for approval.  NERC also submits that  proposed budget of the Western Interconnection Regional Advisory Body and NERC's proposed allocation of the proposed statutory funding requirements of NERC, the Regional Entities and WIRAB by country and among the Regions, and the proposed assessments to the LSEs within each Region to collect the allocated statutory funding requirements.  Docket No. RR08-6-000​

8/22/2008
RM06-16-000, RR08-1-000
Further Compliance Filing in Response to Paragraph 18 of the February 21 Order

NERC submits this further compliance filing in response to the Commission’s February 21, 2008. The Commission directed NERC to work with Bonneville and other federal agencies listed on NERC’s compliance registry to develop procedures that would allow the review of the requested information without risking waiver of FOIA protection. Docket Nos. RM06-16-000 and RR08-1-000.​

8/14/2008
RR08-5-000
Petition for Approval of Amendments to the NERC Bylaws

North American Electric Reliability Corporation submitted a filing to requesting approval of several amendments to NERC’s Bylaws.  Docket No. RR08-5-000​

8/14/2008
RC08-7-000
Motion to Intervene in Compliance Registry Appeal

NERC intervenes and submits comments in the NERC Compliance Registry appeal regarding Constellation Energy Commodities Group, Inc.  Docket No. RC08-7-000​

8/11/2008
RC07-4-003 et al
Compliance Filing of NERC in Response to December 20, 2007 Order

NERC submits its compliance filing in response to the Commission's December 20, 2007 Order and April 4, 2008 Order.  Pursuant to its short-term plan, NERC submits the proposed revisions to the NERC Statement of Compliance Registry Criteria V5-0 for Commission approval.  Docket Nos. RC07-4-003 et al.​

7/31/2008
RR06-1-000
Quarterly Report Regarding Analysis of Reliability Standards Voting Results

NERC submits the Quarterly Report regarding Analysis of Reliability Standards Voting Results April - June 2008.  Docket No. RR06-1-000​

7/31/2008
RM08-13-000
Petition of NERC for Approval of PRC-023-1 Reliability Standard

NERC submits PRC-023-1 - Transmission Relay Loadability Reliability Standard for Commission approval.  Docket Nos. RM08-13-000​

7/30/2008
RM06-22-003
Supplemental Compliance Filing in response to Paragraphs 751 and 757 of Order No. 705

NERC submits Violation Risk Factors for nine requirements and sub-requirements in the Critical Infrastructure Protection Reliability Standards CIP-002-1 through CIP-009-1.  Docket No. RM06-22-003​

7/30/2008
RM08-12-000
Petition for Approval of WECC Regional Reliability Standard and Three Definitions

NERC submits the WECC Regional Reliability Standard, BAL-004-WECC-01 - Automatic Time Error Correction, for Commission approval.  Docket Nos. RM08-12-000​

7/29/2008
RM08-17-000
Errata Petition of NERC for Approval of Two Standards

NERC submits an errata filing that contains corrected versions of two reliability standards: IRO-005-2 and TOP-004-2.  Docket No. RM08-17-000​

7/28/2008
RM06-16-000, RM08-15-000, RM08-16-000
Petition of NERC for approval of Formal Interpretations to Standards

NERC requests the Commission to approve interpretations to requirements of two Reliability Standards: BAL-003-0 and VAR-001-1.  Docket Nos. RM06-16-000, RM08-15-000 and RM08-16-000​

7/28/2008
RC08-4-000
Compliance Filing of NERC in response to the Commission's May 16, 2008 Order

NERC submits this filing in response to the Commission's May 16, 2008 Order regarding NERC's registry decision on New  Harquahala Generating Company, LLC.  Docket No. RC08-4-000​

7/25/2008
RR07-16-004
CORRECTED- Compliance Filing of NERC in response to June 19, 2008 Order

NERC submits this corrected compliance filing in response to the Commission's June 19, 2008 Order regarding the NERC business plan and budget and the business plans and budgets of the eight Regional Entities.  Docket No. RR07-16-004​

7/25/2008
RR07-16-004
Motion of NERC to file Corrected version of the Compliance Filing in response to the June 19 Order

NERC submits a motion to file a corrected version of the Compliance Filing in response to the June 19 Order regarding NERC's and the eight Regional Entities' business plans and budgets.  Docket No. RR07-16-004​

7/25/2008
RR08-4-001
Supplemental Request for Clarification of VSL Order

NERC supplements its July 21 request for clarification and rehearing of the VSL Order.  Docket No. RR08-4-001​

7/23/2008
RR07-14-000
Compliance Filing of NERC in Response to Order on Reliability Enhancement Programs

NERC submits this filing in response to the Commission's November 2, 2007 Order; the filing describes several reliability enhancement programs and activities initiated or expanded in the last year to improve the reliability of the bulk power system.  Docket No. RR07-14-000​

7/21/2008
RR08-4-000
Compliance Filing of NERC in response to Paragraph 40 of the Order on VSLs Proposed by the ERO

NERC submits modifications to Violation Severity Levels for twenty Requirements or Sub-Requirements in the 83 original NERC Reliability Standards.  Docket No. RR08-4-000​

7/21/2008
RR07-16-003
Compliance Filing of the NERC in response to June 19, 2008 Order

NERC submitted additional information regarding the NERC and Regional Entity business plans and budgets in response to Commission directives.  Docket No. RR07-16-003​

7/21/2008
RR06-1-012 et al
Compliance Filing of the NERC in response to March 21, 2008 Order

NERC submits revised Amended and Restated Pro Forma Delegation Agreement with the Regional Entities, revised CMEP, revised Amended and Restated Delegation Agreements with the eight Regional Entities, and certain revisions to the NERC Rules of Procedure.  Docket No. RR06-1-012 et al.​

7/21/2008
RR08-4-000
Request of NERC for Clarification and Rehearing, of the Order on VSLs Proposed by the ERO

NERC requests clarification and rehearing of the Commission's June 18, 2008 Order. Docket No. RR08-4-000​

7/21/2008
RC08-4-000
Unopposed Motion for a Brief Ten Day Extension of Time

NERC requests an extension of time to submit a compliance filing in response to the Commission's May 16, 2008 Order regarding the reliability standards and requirements that will be applicable to New Harquahala Generating Company, LLC.  Docket No. RC08-4-000​

7/21/2008
RM08-11-000
Petition of the NERC for Approval of Three Reliability Standards

(FAC-010-2, FAC-011-2 and FAC-014-2). Docket No. RM08-11-000​

6/30/2008
RM06-22-000
Compliance Filing of the NERC in response to the Paragraph 757 of Order No. 706

Mandatory Reliability Standards for Critical Infrastructure Protection Submission of Revised Violation Risk Factors. Docket No. RM06-22-000​

6/27/2008
RR06-1-012, RR06-1-014, RR07-4-002, RR07-4-003
Motion for a Brief Extension of Time

NERC submits a motion for a brief extension of time to submit a consolidated compliance filing on the ReliabilityFirst Corporation Delegation Agreement.  Docket Nos. RR06-1-012, RR06-1-014, RR07-4-002, and RR07-4-003​

6/27/2008
RC08-1-000
NERC Response to the Commission's February 21, 2008 Order

Remanding Proceedings to the ERO involving Southeastern Power Administration's appeal. Docket No. RC08-1-000​

6/20/2008
RM08-7-000
Comments of the NERC on the NOPR on Modification of Interchange and TLR Reliability Standards; and

Electric Reliability Organization Interpretation of Specific Requirements of Four Reliability Standards.  Docket No. RM08-7-000​

6/12/2008
RC08-5-0006/12/2008
RM05-5-0055/28/2008
RR06-1-012, RR07-3-0025/19/2008
RM06-16-000, RR-08-1-0005/16/2008
RC07-4-002, RC07-6-002, RC07-7-0025/14/2008
RM08-3-0005/13/2008
5/5/2008
RR-06-1-0004/30/2008
RR08-2-0004/21/2008
RM05-17-000, RM05-25-0004/17/2008
RC08-1-0004/16/2008
RM08-7-0004/15/2008
RR07-16-0014/1/2008
RM07-3-000
Compliance Filing of the NERC in Response to Para. 135 of Order No. 705

Facilities Design, Connections and Maintenance Reliability Standards Submission of Revised Violation Risk Factors

Docket No. RM07-3-000
4/1/2008
RC08-4-0003/20/2008
RR07-16-002
Request for Approval of an Amendment to 2008 Business Plan and Budget of the WECC

and for Approval for WECC to Include Loan Repayment and Interest Costs in its 2009 and 2010 Assessments – CORRECTED FILING

Docket No. RR07-16-002
3/17/2008
RC08-4-0003/5/2008
RC08-4-0003/4/2008
RC07-4-000, RC07-6-000, RC07-7-000
Compliance Filing of the NERC in Response to December 20, 2007 Order

Docket Nos. RC07-4-000, RC07-6-000, RC07-7-000​

3/4/2008
RR06-1-007
Compliance Filing of the NERC in Response to the Commission's June 7, 2007 Order

Docket No. RR06-1-007
(Contains: Exhibits A (See amendment filed on March 4, 2008 for complete Exhibit A), C, and D) Docket No. RR08-4-000

3/3/2008
RR07-16-000
Approval of an Amendment to the 2008 Business Plan and Budget of the WECC

Request of the North American Electric Reliability Corporation for Approval of an Amendment to the 2008 Business Plan and Budget of the Western Electricity Coordinating Council and for Approval for WECC to Include Load Repayment and Interest Costs in its 2009 and 2010 Assessments.
Docket No. RR07-16-​000

2/15/2008
RM06-16-0002/1/2008
RR06-1-0001/31/2008
RC07-4-000, RC07-6-000, RC07-7-000
Request for Clarification of December 20, 2007 Order by NERC

Docket Nos. RC07-4-000, RC07-6-000, and RC07-7-000​

1/22/2008
 

home | account log-in/register | legal and privacy/trademark policy | site map | careers | contact us

Atlanta Office | 3353 Peachtree Road, NE Suite 600 North Tower, Atlanta, GA 30326 | 404-446-2560
Washington Office | 1325 G Street, NW Suite 600, Washington, DC 20005| 202-400-3000

Copyright 2016 North American Electric Reliability Corporation. All rights reserved.