Event Summary |
FILE SAVED AS: PJM_310_20100129_1215.htm
|
|
Incident:
|
PJM_310_20100129_1215
|
Date: 01/29/2010
|
Reliability Coordinator: PJM
|
|
Initial Conditions:
|
N/A
|
|
Flowgate:
|
310 - Person-Halifax 230 kV line l/o...
|
Rating: 0
|
LODF: 24.31%
|
|
TLR Direction:
|
Normal
|
|
Effective StartTime:
|
01/29/2010 12:15
|
Effective EndTime: 01/29/2010 18:50
|
TLR Duration: 6 Hours and 35 Minutes
|
|
TLR Actions |
Jan 29 11:47
|
TLR 3A
|
NEXT
|
|
|
1 / 0
|
|
1 / 0
|
|
23 / 0
|
|
25 / 0
|
|
|
|
|
|
|
|
NONE
|
|
|
|
|
0
|
0
|
0
|
Jan 29 12:30
|
TLR 3A
|
NEXT
|
|
|
|
|
|
|
|
|
NONE
|
|
|
|
|
0
|
0
|
0
|
Jan 29 13:23
|
TLR 1
|
CURRENT
|
NONE
|
NONE
|
NONE
|
0
|
0
|
0
|
Jan 29 18:39
|
TLR 0
|
CURRENT
|
NONE
|
NONE
|
NONE
|
0
|
0
|
0
|
|
|
|
TLR Schedule Totals |
| 0 |
0 |
0 |
0 |
0 |
| 1 |
3 |
95 |
95 |
0 |
| 2 |
3 |
271 |
271 |
0 |
| 3 |
0 |
0 |
0 |
0 |
| 4 |
0 |
0 |
0 |
0 |
| 5 |
0 |
0 |
0 |
0 |
| 6 |
23 |
391 |
391 |
50 |
| 7 |
0 |
0 |
0 |
0 |
| Total |
29 |
757 |
757 |
50 |
|
|
|
TLR Market Flow Totals |
| PJM |
ED-2 |
0.0 |
0.0 |
| ED-6 |
0.0 |
0.0 |
| FIRM-7 |
3.6 |
3.6 |
| Total for PJM |
3.6 |
3.6 |
| Total |
3.6 |
3.6 |
|
|
| |
|