Recommendation to Industry:
Consideration of Actual Field Conditions in
Determination of Facility Ratings
On November 30, 2010, NERC provided an update to
the October 7, 2010 Recommendation to Industry
entitled “Consideration of Actual Field
Conditions in Determination of Facility
Ratings.” Transmission Owners and Generator
Owners of bulk electric system facilities should
review their current facility ratings
methodology for their transmission lines to
verify the methodology used is based on actual
field conditions and determine if their ratings
methodology will produce appropriate ratings
when considering differences between design and
field conditions. If entities have not
previously verified that the facility design,
installation, and field conditions are within
design tolerances when the facilities are loaded
at their ratings, entities are required by
January 18, 2011, to describe its plans to
complete such an assessment of all its
transmission lines, with the highest priority
lines assessed by December 31, 2011, medium
priority lines by December 31, 2012, and the
lowest priority by December 31, 2013. At the
conclusion of each year, each Transmission Owner
and Generator Owner must report to its Regional
Entity a summary of the assessments and
identification of all transmission facilities
where as-built conditions are different from
design conditions, resulting in incorrect
ratings, and their associated mitigation
timelines. Remediation is expected within one
year from identification of the issue or on a
schedule approved by the Regional Entity if
longer than a year.
Owners are also expected to coordinate
with their respective operating and planning
organizations to coordinate interim mitigation
strategies.
|