WECC Request for
Interpretation - BAL-001 and BAL-003
Status:
The interpretation of
BAL-001 R1 and BAL-003 R3 was approved by stakeholders and the NERC
Board of Trustees and received regulatory approval on July 21, 2008.
Purpose/Industry Need:
The Western
Electricity Coordinating Council (WECC) requests an interpretation
applicable to the NERC standard requirements BAL-001-0, R1 and
BAL-003-0, R3. Specifically, the WECC asks that NERC conclude and
confirm that the WECC's Automatic Time Error Control Procedure (ATEC)
does not violate NERC standards. This interpretation would permit the
continued use of WECC's ATEC within the Western Interconnection
|