Project 2009-10
Interpretation
− PRC-005-1, R1 −
CMPWG
Status:
The interpretation was approved by the NERC Board of Trustees on
November 5, 2009.
Summary:
The request asks for clarification on the following:
-
Does R1 require a maintenance and testing program for the battery
chargers for the “station batteries” that are considered part of the
Protection System?
-
Does R1 require a maintenance and testing program for auxiliary
relays and sensing devices? If so, what types of auxiliary relays
and sensing devices? (i.e. transformer sudden pressure relays)
-
Does R1 require maintenance and testing of transmission line
re-closing relays?
-
Does R1 require a maintenance and testing program for the DC
circuitry that is just the circuitry with relays and devices that
control actions on breakers, etc., or does R1 require a program for
the entire circuit from the battery charger to the relays to circuit
breakers and all associated wiring?
-
For R1, what are examples of
"associated communications systems" that are part of “Protection
Systems” that require a maintenance and testing program?
Purpose/Industry Need:
In accordance with the Reliability Standards
Development Procedure, the interpretation must be posted for a 30-day
pre-ballot review, and then balloted.
There is no public comment period for an interpretation.
Balloting will be conducted following the same method used for
balloting standards.
If the interpretation is approved by its ballot pool, then the
interpretation will be appended to the standard and will become
effective when adopted by the NERC Board of Trustees and approved by the
applicable regulatory authorities. The interpretation will remain
appended to the standard until the standard is revised through the
normal standards development process.
When the standard is revised, the clarifications provided by the
interpretation will be incorporated into the revised standard.
|