Purpose/Industry Need:
Florida Municipal Power Pool
(FMPP) is seeking clarification as to whether Requirement R10 requires
the BA to plan to maintain load-interchange-generation balance under the
direction of the TOPs for meeting all SOLs and IROLs.
In accordance with the Reliability Standards
Development Procedure, the interpretation must be posted for a 30-day
pre-ballot review, and then balloted.
There is no public comment period for an interpretation.
Balloting will be conducted following the same method used for
balloting standards.
If the interpretation is approved by its ballot pool, then the
interpretation will be appended to the standard and will become
effective when adopted by the NERC Board of Trustees and approved by the
applicable regulatory authorities. The interpretation will remain
appended to the standard until the standard is revised through the
normal standards development process.
When the standard is revised, the clarifications provided by the
interpretation will be incorporated into the revised standard.
|