Project 2010-13.2: Relay Loadability Order
Related Files
Status:
The standard and implementation plan
and approved the VRFs and VSLs were approved by the NERC Board of
Trustees on March 10, 2011.
Background:
As the ERO, NERC must address all directives in Orders issued by FERC.
On March 18, 2010 FERC issued
Order No. 733 which approved Reliability Standard PRC-023-1 –
Transmission Relay Loadability, and also directed NERC, as the Electric
Reliability Organization (“ERO”), to develop certain modifications to
the PRC-023-1 standard through its Reliability Standards development
process, to be completed by specific deadlines. Attachment 1 to the SAR
contains the directives and associated deadlines. The Order also
directed development of two new Reliability Standards to address issues
related to generator relay loadability and the operation of protective
relays due to power swings. The standards-related directives in Order
733 are aimed at closing some reliability-related gaps in the scope of
PRC-023-1.
This
SAR’s scope includes three standard development phases to address the
standards-related directives in Order No. 733 directives. Phase I is
focused on making the specific modifications to PRC-023-1 that were
identified in the order; Phase II is focused on developing a new
standard to address generator relay loadability; and Phase III is
focused on developing requirements that address protective relay
operations due to power swings.