Project 2010-13.2: Relay Loadability Order

Related Files

Status: 

The standard and implementation plan and approved the VRFs and VSLs were approved by the NERC Board of Trustees on March 10, 2011.

 

Background:

As the ERO, NERC must address all directives in Orders issued by FERC.  On March 18, 2010 FERC issued Order No. 733 which approved Reliability Standard PRC-023-1 – Transmission Relay Loadability, and also directed NERC, as the Electric Reliability Organization (“ERO”), to develop certain modifications to the PRC-023-1 standard through its Reliability Standards development process, to be completed by specific deadlines. Attachment 1 to the SAR contains the directives and associated deadlines. The Order also directed development of two new Reliability Standards to address issues related to generator relay loadability and the operation of protective relays due to power swings. The standards-related directives in Order 733 are aimed at closing some reliability-related gaps in the scope of PRC-023-1.

This SAR’s scope includes three standard development phases to address the standards-related directives in Order No. 733 directives. Phase I is focused on making the specific modifications to PRC-023-1 that were identified in the order; Phase II is focused on developing a new standard to address generator relay loadability; and Phase III is focused on developing requirements that address protective relay operations due to power swings.

 

Draft Action Dates Results Consideration of Comments
 

D
raft PRC-023-2

Clean | Redline to last posting
Redline to last approval

Implementation Plan
Clean | Redline to last posting



Recirculation Ballot
 
Info>>

Vote>>
 02/24/11 - 03/07/11 Summary>>

Full Record>>
Consideration of Comments


PRC-023-2

Clean | Redline to last posting

Redline to last approval

Implementation Plan

Clean | Redline to last posting

Supporting Materials

VRF/VSL Justification

Mapping Document




Successive Ballot
Info>>

Vote>>



01/24/11 - 02/14/11





Summary>>


Full Record>>






Consideration of Comments>>
Non-Binding Poll
Info>>

Vote>>
01/24/11 - 02/13/11
Non-Binding Poll Results>>


Consideration of Comments>>

 

 

 

 

 

 

 

 

SAR for Relay Loadability

clean | Redline to last posting

 

PRC-023-2

Clean | Redline to last posting

Redline to last approval

 

Implementation Plan

Clean

Supporting Materials:

Comment form (Word)

Intial Ballot


Info>>

Vote>>
12/07/10 - 12/16/10
(closed)
Summary>>

Full Record>>
Consideration of Comments>>

Ballot Pool

 Info>>

 

 

11/01/10 - 12/02/10
(closed)
   

45-day Formal

Comment Period

Info>>

 Submit Comments>>

 

11/01/10 – 12/16/10
(closed)
Comments Received>> Consideration of Comment>>

PRC-023- Attachment B

Supporting Materials:

Comment form (Word)

Comment Period

Info>>

Submit Comments>>

9/23/10 - 10/12/10
(closed)
Comments Received>> Consideration of Comments >>

 Draft 1

SAR for Relay Loadability Modifications and Additions
PRC-023-2

Draft SAR Version 1

 

Supporting Materials:

Comment Form (Word)

PRC-023-2
clean
| redline to last approval

 

 

 Comment Period

Info>>

Submit Comments>>

 

 

08/19/10 - 09/19/10
(closed)
Comments Received>> Consideration of Comments >>

All comments should be forwarded to sarcomm@nerc.net.