MOD-025-1 |
Verification of Generator Gross and Net Reactive Power Capability |
Phased-in
Implementation:
Requirement 1 and Requirement 2 January 1, 2007
Requirement
3:
January 1, 2008 1st 20% compliant
January 1, 2009 2nd 20% compliant
January 1, 2010 3rd 20% compliant
January 1, 2011 4th 20% compliant
January 1, 2012 5th 20% compliant |
01/01/07 |
|
Nuclear
|
|
NUC-001-1 |
Nuclear Plant Interface
Coordination |
First
day of first quarter 15 months after applicable regulatory approvals. |
05/02/07 |
Archive
|
|
Organization Certification |
|
|
|
|
|
|
Personnel Performance, Training, and Qualifications |
|
PER-001-0 |
Operating Personnel
Responsibility and Authority |
04/01/05 |
Archive |
|
PER-002-0 |
Operating Personnel Training |
04/01/05 |
|
PER-003-0 |
Operating Personnel
Credentials |
04/01/05 |
|
PER-004-1 |
Reliability Coordination
Staffing |
01/01/07 |
Archive
|
|
Protection and
Control |
|
PRC-001-1 |
System Protection Coordination |
01/01/07 |
Archive
|
|
PRC-002-1 |
Define and Document
Disturbance Monitoring Equipment Requirements |
05/02/07 |
Archive |
|
PRC-003-1 |
Regional Requirements for Transmission and Generation
Protection System Misoperations |
05/01/06 |
Archive |
|
PRC-004-1 |
Analysis and Mitigation of Transmission and Generation
Protection System Misoperations |
08/01/06 |
|
PRC-005-1 |
Transmission and Generation Protection System
Maintenance and Testing |
05/01/06 |
|
PRC-006-0 |
Development and Documentation
of Regional UFLS Programs |
04/01/05 |
Archive |
|
PRC-007-0 |
Assuring Consistency with
Regional UFLS Program Requirements |
04/01/05 |
|
PRC-008-0 |
Underfrequency Load Shedding
Equipment Maintenance Programs |
04/01/05 |
|
PRC-009-0 |
UFLS Performance Following an
Underfrequency Event |
04/01/05 |
|
PRC-010-0 |
Assessment of the Design and
Effectiveness of UVLS Program |
04/01/05 |
|
PRC-011-0 |
UVLS System Maintenance and
Testing |
04/01/05 |
|
PRC-012-0 |
Special Protection System
Review Procedure |
04/01/05 |
|
PRC-013-0 |
Special Protection System
Database |
04/01/05 |
|
PRC-014-0 |
Special Protection System
Assessment |
04/01/05 |
|
PRC-015-0 |
Special Protection System Data
and Documentation |
04/01/05 |
|
PRC-016-0 |
Special Protection System
Misoperations |
04/01/05 |
|
PRC-017-0 |
Special Protection System
Maintenance and Testing |
04/01/05 |
|
PRC-018-1 |
Disturbance Monitoring
Equipment Installation and Data Reporting |
Phased
in over four years after BOT adoption:
Requirements
1 and 2:
-
50% compliant two years
after initial issuance of regional requirements per RELIABILITY STANDARD
PRC-002 Requirement 5.
-
75% compliant three years
after initial issuance of regional requirements per reliability standard
PRC-002 R5.
-
100% compliant four years
after initial issuance of regional requirements per reliability standard
PRC-002
R5.Requirements 3 through
6:
-
100% compliant six months
after BOT adoption for already installed DME.
-
100% compliant six months
after installation for DMEs installed to meet Regional Reliability
Organization requirements per reliability standard PRC-002 Requirements 1, 2
and 3.
|
08/02/06 |
Archive |
|
PRC-020-1 |
Under-Voltage Load Shedding Program Database |
05/01/06 |
|
PRC-021-1 |
Under-Voltage Load Shedding Program Data |
08/01/06 |
|
PRC-022-1 |
Under-Voltage Load Shedding Program Performance |
05/01/06 |
|
PRC-023-1 |
Transmission Relay
Loadability |
02/12/08 |
Archive
|
|
Transmission
Operations |
|
TOP-001-1 |
Reliability Responsibilities
and Authorities |
01/01/07 |
Archive
|
|
TOP-002-2 |
Normal Operations Planning |
01/01/07 |
Archive
|
|
TOP-003-0 |
Planned Outage Coordination |
04/01/05 |
Archive |
|
TOP-004-1 |
Transmission Operations |
10/01/07 |
Archive
|
|
TOP-004-2 |
Transmission Operations |
01/01/09 |
|
|
TOP-005-1 |
Operational Reliability
Information |
11/01/06 |
Archive |
|
TOP-006-1 |
Monitoring System Conditions |
01/01/07 |
Archive
|
|
TOP-007-0 |
Reporting SOL and IROL
Violations |
04/01/05 |
Archive |
|
TOP-008-1 |
Response to Transmission Limit
Violations |
01/01/07 |
Archive
|
|
Transmission
Planning |
|
TPL-001-0 |
System Performance Under
Normal Conditions |
04/01/05 |
Archive |
|
TPL-002-0 |
System Performance Following Loss of a Single BES
Element |
04/01/05 |
|
TPL-003-0 |
System Performance Following
Loss of Two or More BES Elements |
04/01/05 |
|
TPL-004-0 |
System Performance Following
Extreme BES Events |
04/01/05 |
|
TPL-005-0 |
Regional and Interregional
Self-Assessment Reliability Reports |
04/01/05 |
|
TPL-006-0 |
Assessment Data from Regional
Reliability Organizations |
04/01/05 |
|
Voltage and Reactive |
|
VAR-001-1a |
Voltage and Reactive Control
Interpretation (Archive)
|
02/02/07 |
Archive |
|
VAR-002-1a |
Generator Operation for Maintaining Network
Voltage Schedules
Interpretation (Archive)
|
08/02/07 |
|
To download a file click on the file using your right mouse button, then save
it to your computer in a directory of your choice. |
 |
Documents in the PDF format
require use of the Adobe Readerฎ
software. Free
Adobe Readerฎ software allows anyone view and print Adobe
Portable Document Format (PDF) files. For more
information download the
Adobe Reader User Guide.
|